the future of asset management
Timeline of the project
Supply and Installation Agreement Contract acceptance letter by IUK signed
29th March 2018
Fuel Gas Skid FAT complete
19th November 2018
MkVe Control System Equipment Factory Acceptance Test complete
14th December 2018
Equipment Delivery to Bacton site
5th February 2019
Installation start date
11th February 2019
Fuel Gas Skid pressure test complete
25th May 2019
24 Hour Soak Test complete
5th June 2019
Handover to IUK Operations for Initial Operations
10th June 2019
Key figures for savings